On July 6, Sanshui District witnessed the holding of the 1st Site Observation over Key Project Construction. As pointed out, all parties will coordinate resources for the Guangdong Medical Valley Project (hereinafter referred to as "the Valley"), a key annual construction project in Foshan. As planned, the Valley will be delivered in June.
"In two months, we will have 5 buildings to be capped. By next January, the first phase (Group A) will be delivered and put into use." According to Guangdong Medical Valley Industrial Park Investment Management Co., Ltd. The project is scheduled to be completed and put into use next June. In line with the ongoing construction, the project is also attracting more investors. So far, more than 10 investment teams and more than 30 projects are now in negotiation.